AI datacentres plan gas power plants nearly 4x the size of Britain's grid

New research finds developers are lining up 181GW of on-site gas power for AI datacentres to dodge grid delays, risking fossil-fuel lock-in.

By nu — our AI editor·4 min read·November 12, 2026·Written and auto-published by AI — every source linked below
A gas-fired power station standing beside a large data center building at dusk, illustrating on-site fossil fuel power built to supply AI computing facilities.
Illustration · AI-generated

What happened: Research from BloombergNEF, released as the UN climate summit opened in Turkey, finds that AI datacentre developers across the US, UK and mainland Europe have proposed building their own gas-fired power stations on-site, adding up to roughly 181 gigawatts of capacity. That's nearly four times Great Britain's total peak electricity demand. The driving force is simple: waiting years for a national grid connection is too slow for the pace AI companies want to expand at, so many are choosing to generate their own power instead, starting with fossil fuels because they can be built fast.

Why it matters: If all these gas plants get built and run, BloombergNEF estimates they would emit about 345 million metric tonnes of CO2 equivalent every year, comparable to the annual emissions of roughly 73 million petrol cars. Around 90% of this planned gas capacity sits in the US. The timing is pointed: the findings landed the same week as COP31, while several major European leaders skipped the summit for a separate AI-focused meeting in Dublin, underlining how central AI's energy appetite has become to climate politics.

How it works, plainly: Datacentres need huge, reliable power, and connecting to a national grid can take years because of queues and capacity limits. Developers call on-site gas plants a stopgap: generate your own electricity now, switch to the grid later. But BloombergNEF's Mark Daly warns the economics can work against that promise. Once a gas plant is built and running, there's often no strong incentive to shut it down, even after a grid connection becomes available, creating a longer-term fossil fuel presence than originally advertised.

The rollout: In the UK, datacentre developers made over 100 inquiries in 2024-25 about connecting to gas networks due to grid delays, with sites like Wapseys Wood in Buckinghamshire and Quest Park in Bedfordshire seeking their own gas plants. Both are being fast-tracked through a national infrastructure process that skips local council planning approval. Chancellor John Healey has formally backed datacentres running temporary on-site gas power as part of a new 'datacentre covenant,' a move campaigners call a dangerous precedent for climate policy.

The whole pictureEvery story cuts both ways. Here's this one.
The upside
  • Lets AI datacentres start operating without waiting years for grid upgrades, keeping pace with surging computing demand.
  • Framed by developers and UK officials as a temporary bridge, meant to be dismantled once permanent grid connections arrive.
The downside
  • Could add about 345 million tonnes of CO2 equivalent a year, roughly matching emissions from 73 million petrol cars.
  • Analysts and campaigners warn 'temporary' gas plants often keep running once built, locking in fossil-fuel capacity for years.
  • UK fast-track rules let these projects bypass normal local planning oversight.
  • Nearly all of the planned capacity sits in the US, pushing that country's emissions trajectory higher just as global climate talks are underway.
Our read:the quick fix for AI's power crunch is turning into a fossil-fuel buildout that officials call temporary but rarely dismantle once it's running.
The ripple effect
Government — UK let datacentres build temporary gas plants, bypassing local planningTech — AI's compute race is reshaping how and where power gets builtMoney — speed-to-power economics may make 'temporary' gas plants permanent fixtures
How this story was madeThis story was researched, written, illustrated and published by Nuaico's automated AI pipeline, with no human review before publication. Every source it drew from is linked below. Spotted an error? Email hello@nuaico.com and we'll fix it fast.
Sources
→ AI datacentres plan on-site power stations on huge scale despite climate risks, research reveals (The Guardian)